City Council to approve capital accounts Wednesday for Sports- og Kulturcampus and move 2.53 million kr. to defect rectification

AI-written · beta

On Wednesday, 18 November 2026, Aarhus City Council will consider the recommendation to approve the capital accounts for Sports- og Kulturcampus in Gellerup and transfer underspending of 2.53 million kr. to a temporary KB appropriation for follow-up, defect rectification and completion through the end of 2029.

  • Kultur og fritid
  • Økonomi og budget
  • Byudvikling og lokalplan
Document date
Section
City council
Status
Beta

Summary

On Wednesday, 18 November 2026, Aarhus City Council will consider the recommendation to approve the capital accounts for Sports- og Kulturcampus in Gellerup and transfer underspending of 2.53 million kr. to a temporary KB appropriation for follow-up, defect rectification and completion through the end of 2029.

What it means for you

The campus is already in use as a sporting, cultural and social hub with six facilities. The proposed set-aside is intended, among other things, to fix access control, building systems and practical issues in Bevægelseshuset so technical operations become more efficient and users’ day-to-day experience improves.

Background

Culture and Citizen Services recommends that the byråd (city council) approve the capital accounts for construction and at the same time earmark the underspending. All capital expenditures have been incurred, all income from foundations and contributors has been received, and the capital appropriation has been adhered to.

The City Council has addressed the establishment several times since 2016. The capital appropriation was granted in 2019, and the facilities were taken into use in December 2021. The accounts must go to the city council because the project’s expenditure exceeds 50 million kr.

The campus comprises Kunstgræsbanen, Byparken, Verdenspladsen, Gellerup Bibliotek, Samlingshuset and Bevægelseshuset. The capital accounts for Kunstgræsbanen and Byparken were submitted earlier; Samlingshuset is financed by Brabrand Boligforening. The project was carried out in collaboration between Culture and Citizen Services, Brabrand Boligforening, Gøglerskolen/FGU-Aarhus and Health and Care, with grants from Lokale- og Anlægsfonden and Salling Fondene.

After handover, technical follow-up and defect rectification remain outstanding. The five-year inspection takes place in autumn 2026. Municipal spending on matters outside the contractors’ responsibility is estimated at around 1.5 million kr., while around 1 million kr. is proposed for building adjustments in Bevægelseshuset, including access to a costume room and installation of a gate.

Figures and facts

Who said what

Alderman (rådmand) Jesper Kjeldsen and acting director Lise Uhre Pless submit the recommendation from Culture and Citizen Services of 21 October 2026. The Mayor’s Office has no comments. The Municipal Executive recommended on 10 November 2026 that the city council endorse the recommendation.

What happens next

Aarhus City Council will consider the recommendation on Wednesday, 18 November 2026. If the city council endorses it, the capital accounts are approved and the underspending is transferred to the KB appropriation for follow-up, defect rectification and adjustment in dialogue between Culture and Citizen Services and Aarhus Ejendomme through the end of 2029.

Sources

AI-written news (beta), based on Aarhus Municipality's public agendas, supporting documents and minutes. It doesn't replace the municipality's official documents — follow the source links.

Published after the document date: onsdag den 18. november 2026. Spotted a mistake? tbj@bona.city.