City Council considers DKK 12.4 million for design of new special school in Lisbjerg
AI-written · beta
On Wednesday 18 November 2026, Aarhus City Council will consider a proposal for a capital grant of DKK 12.4 million for the design of a new special school in Lisbjerg.
- Skole og dagtilbud
- Økonomi og budget
- Byudvikling og lokalplan
- Document date
- Section
- City council
- Status
- Beta
Summary
On Wednesday 18 November 2026, Aarhus City Council will consider a proposal for a capital grant of DKK 12.4 million for the design of a new special school in Lisbjerg. The total capital framework is DKK 327.3 million, and the school is expected to be ready for the start of the 2031/32 school year.
What it means for you
Families with children in Stensagerskolen’s target group will eventually get a specialised school offer in Lisbjerg, closer to home in the northern part of the municipality. The proposal is about design work first; the actual construction will require a grant decision later. Opening is one year later than the original political target of school start in 2030/31.
Background
The Technical and Environmental Committee and the Children and Young People Committee propose that byråd (city council) grant capital funding for design, allocate availability amounts over three years, and move the remaining availability amount to the capital reserve. The Municipal Executive recommended on 10 November 2026 that the city council adopt the proposal of 23 October 2026. The Mayor’s Department has no comments.
The coalition parties agreed in the capital agreement Et aktivt og grønt Aarhus for alle from 20 June 2025 that a new special school would be built in Lisbjerg for Stensagerskolen’s target group. It is to replace the temporary capacity at Stensagervej 11, 8260 Viby J, which was brought into use at the start of the 2024/25 school year and currently houses six final-year classes with about 50 pupils.
The background is rising demand for special school places. Both Stensagerskolen and Langagerskolen are seeing increasing pupil numbers. Under the Primary Education Act, the municipality must be able to offer special-needs education without waiting lists.
The school is planned as an independent two-track special school with capacity for 180 pupils, plus SFO and club, and with land reserved for later expansion to three tracks and any other special offers. It will be established as a sister school with the same profile as Stensagerskolen at Janesvej 2, 8220 Brabrand. The Lisbjerg location is intended, among other things, to cut travel time for pupils in the north. The pupil’s home address is an important factor in placement decisions between the two schools.
The school will be built with a total floor area of about 8,550 m² as part of phase 2 of the development plan for Lisbjerg. SFO will be integrated; the club will be set up in a shared facility with the school. The project is prepared for later expansion from 180 to 270 pupils. Land is also reserved for possible special day-care and STU offers; these are not part of the current capital budget.
The consultant tender ran from May to September 2026, with the contract conditional on city council approval. Next steps are a building programme, then a design-and-build tender from April 2027 to January 2028, design in 2028, and construction from the first half of 2029 to mid-2031. Work on the local development plan (lokalplan) runs in parallel. Technical and Environmental assesses that the schedule cannot be compressed further without greater risk to cost and progress.
Figures and facts
- Capital grant for design: DKK 12.4 million (Appendix — Proposal)
- Availability amount for design: DKK 5 million in 2026, DKK 4.5 million in 2027, and DKK 2.9 million in 2028 (Appendix — Proposal)
- Remaining availability amount to capital reserve: DKK 314.9 million (Appendix — Proposal)
- Total capital expenditure estimated: DKK 327.3 million in 2026 prices, including DKK 26.6 million for land purchase (Appendix — Proposal)
- Capacity: 180 pupils (two tracks); option for later 270 pupils (three tracks); about 8,550 m² (Appendix — Proposal)
- Expected construction price per square metre: DKK 35,170; land purchase DKK 2,062 per construction square metre (Appendix — Appendix 2: Key figures for unit prices)
What happens next
City Council will consider the proposal on Wednesday 18 November 2026. The Municipal Executive recommends that City Council adopt it. If the proposal is adopted, design work begins, and City Council will later receive a new proposal on the remaining capital grant once design has progressed sufficiently.
Sources
- Agenda — New special school in Lisbjerg
- Appendix — Proposal
- Appendix — Appendix 2: Key figures for unit prices
- Aarhus Municipality meeting documents — meeting
- Aarhus Kommune